All closures / Why they close / Cause not stated

Cause not stated

Cruising-season closures outside CRT's winter programme, with this cause: 7 in June to August 2026 against 3 a year earlier, within what chance produces; tested on its own, not among the trends page's findings. How a change is tested.

On record
22 closures since May 2025

In force today

1 closure with this cause is in force today, longest shut first. Filter the explorer to them.

Shut today, counted to today.
CanalWhereSinceDays shut
South Stratford CanalLock 22 to Lock 55, Warwick Road3 August 202654

By canal

15 canals have had a closure with this cause. A closure naming two canals counts on both.

Closures with this cause on each canal since May 2025, most first.
CanalClosures
Lee Navigation3
Oxford Canal3
Regent's Canal2
South Stratford Canal2
Staffordshire & Worcestershire Cnl2
Bridgwater & Taunton Canal1
Calder & Hebble Navigation1
Erewash Canal1
Grand Union Canal1
Hertford Union Canal1
Kennet & Avon Canal1
Old River Lea1
Show 3 moreShow fewer
CanalClosures
Peak Forest Canal1
River Stort1
Sheffield & Tinsley Canal1

Every closure on record

Showing 22 closures whose cause reads “Cause not stated”.

Period

Rank by

Population

5 closures are in neither group: 5 unplanned with no day in the cruising season since May 2025.

Status

Duration

Cause

Asset affected

Lock part

Unplanned lock failures naming a part

Water problem

Unplanned failures naming one

CRT reason

Region

22
closures
192
closure-days since May 2025
188
in cruising season
1
no reopening date
What these figures mean
Population
Which closures a figure counts. All closures is everything; Unplanned closure drops the works CRT flags as its winter programme and any day outside the cruising season (the Friday nearest 15 March to the Sunday before the first Monday in November). Scheduled work CRT does not flag as winter works still counts here. CRT Planned closure is the flagged winter programme alone.
Defensible duration
The days between a closure's start and its reopening date, counted only where the dates allow it. A cancelled notice, or one whose reopening precedes its start, has no defensible duration and is in no total.
Closure-days
One day on which one closure was in force. Two closures on the same day are two closure-days; where the question is how long a canal was actually disrupted, overlapping notices are unioned into single intervals. They are counted from 1 May 2025, when this archive begins: a closure that started earlier adds only its days since then, though its own row shows its whole length. Every figure and chart counts only the days inside the Period chosen above them.
In force
A closure is in a Period, and a day is one a closure affected, if it was in force at any time that day, including the morning it reopened. Closure-days measure how long, so they count whole days and not the reopening day: a closure can be in a Period and add no closure-day to it.

Closures in force each month

closures active during the month
3
1
2
2
0
0
1
2
0
1
1
3
1
2
4
2
1
May 25Jun 25Jul 25Aug 25Sep 25Oct 25Nov 25Dec 25Jan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26

Canals ranked by the season's closures

share of the period's cruising-season days up to today — a closure somewhere on a long canal is likelier, and does not mean the canal was impassableclosures in force on the period's cruising-season days — a longer canal has more to go wrong on

Where

closure-days by regionclosures by region

A region with more canal has more to go wrong on, so these totals partly measure its size. Regions compared by length of canal are on the Reliability page.

CRT's reason

closure-days by the reason CRT filedclosures by the reason CRT filed

What fails

closure-days by assetclosures by asset

What fails on a lock

closure-days by part — unplanned lock failures naming a partclosures by part — unplanned lock failures naming a part

How long they last

closures by full length, including any days before May 2025 — the bands are not equal in width
11
8
0
2
0
1
<=1d2-7d8-30d31-90d91-365d>365d
22 results · every closure whose cause reads “Cause not stated”Jump to list

Closures

  1. Albert Street Cutting. Bridgwater & Taunton Canal

    Bridgwater & Taunton CanalWales and South West

    1,337 days

    From 12 November 2021

    Reopened 11 July 2025

    71 of them since this archive began on 1 May 2025

    Where
    Bridge 1, Victoria Rd to Bridge 4, Albert St
    CRT reason
    Repair
    Cause
    Cause not stated
    Asset
    Canal or river

    Please be advised that following planned inspection works through Albert Street Cutting the Trust has taken the decision to close the towpath and navigation with immediate effect in the interest of public safety. We are working with colleagues to ensure that remedial work to…

    CRT's only update, 1 May 2025.

  2. Lock 22 Lapworth to Lock 55 Stratford upon Avon

    South Stratford CanalWest Midlands

    54 days

    Fully shut 54 of CRT's 54 days

    From 3 August 2026

    No reopening date

    Still shut

    Where
    Lock 22 to Lock 55, Warwick Road
    CRT reason
    Low Water Levels
    Cause
    Cause not stated
    Asset
    Canal or river

    The South Stratford Canal will be closed to navigation between Lock 22, Lapworth and Lock 55, Stratford upon Avon from Monday 3 August 2026 until further notice. This temporary closure will help conserve water and allow the affected section to recover, supporting the…

    CRT's only update, 20 July 2026. 68 days without another.

  3. Tinsley Flight - closed due to low water levels.

    Sheffield & Tinsley CanalYorkshire and North East

    32 days

    From 3 July 2026

    Reopened 4 August 2026

    Where
    Lock 1 Tinsley to Tinsley Lock 1 Basin
    CRT reason
    Low Water Levels
    Cause
    Cause not stated
    Asset
    Canal or river

    The water levels along the Tinsley flight have almost recovered to a navigable level. Due to this we will be taking bookings for Tuesday the 4th of August onwards. Please contact the customer service team on 0303 040 4040 to make a booking.

    Latest of 9 CRT updates, 31 July 2026.

  4. Navigation Closure - Lee Navigation, Lock 10, Waltham Common Lock and Lock 9, Cheshunt Lock, Cheshunt

    Lee NavigationLondon and South East

    7 days

    From 20 August 2025

    Reopened 27 August 2025

    Where
    Lock 10, Waltham Common Lock to Lock 9, Cheshunt Lock
    CRT reason
    Inspections
    Cause
    Cause not stated
    Asset
    Lock

    Unfortunately we've had to move this closure ahead of schedule based upon new data from the Environment Agency. We will closing all navigation between Lock 10 and Lock 9 from the 20th of August at 15:30pm and reopening at 27th of August at 09:00am. We will be reviewing this…

    Latest of 2 CRT updates, 19 August 2025.

  5. Low water levels between Lock 6 Sheering Mill Lock and Lock 7, Feakes Lock.

    River StortLondon and South East

    7 days

    Fully shut 7 of CRT's 8 days

    From 18 May 2026

    Reopened 26 May 2026

    Where
    Lock 7, Feakes Lock to Lock 6, Sheering Mill Lock
    CRT reason
    Low Water Levels
    Cause
    Cause not stated
    Asset
    Canal or river

    Following further inspections we've closed the pound between Lock 7 and Lock 6 until necessary repairs have been undertaken. We'll update this notice with more information on Monday the 25th of June.

    Latest of 2 CRT updates, 19 May 2026.

  6. City Road Lock closure

    Regent's CanalLondon and South East

    6 days

    Fully shut 6 of CRT's 11 days

    From 25 April 2025

    Reopened 6 May 2025

    none of them since this archive began on 1 May 2025

    Where
    Lock 5, City Road Lock
    CRT reason
    Suspected Vandalism
    Cause
    Cause not stated
    Asset
    Lock

    We are pleased to announce that we have now got everything in place to be able to offer assisted passage through City Road Lock for single narrow craft only. The days/times are as follows: Thursday 1st May 2025 1030 1400 Friday 2nd May 2025 1030 1400 Saturday 3rd May 2025 1030…

    CRT's only update, 6 May 2025.

  7. Navigation Closure - Hertford Union Canal, Top Lock, Lock 1 - Bottom Lock, Lock 3, Bow / Hackney Wick

    Hertford Union CanalLondon and South East

    5 days

    From 20 July 2026

    Reopened 25 July 2026

    Where
    Lock 1, Top Lock to Lock 3, Bottom Lock
    CRT reason
    Low Water Levels
    Cause
    Cause not stated
    Asset
    Canal or river

    We are pleased to advise the Hertford Union will re-open for navigation commencing 25th July 2026 at 08:00 hours.

    Latest of 2 CRT updates, 24 July 2026.

  8. Navigation Closure, Hardmead Lock - Lock 3

    Lee NavigationLondon and South East

    3 days

    From 19 December 2025

    Reopened 22 December 2025

    Where
    Lock 3, Hardmead Lock
    CRT reason
    Underwater Obstruction
    Cause
    Cause not stated
    Asset
    Lock

    Due to an obstruction on the cill we've closed Hardmead Lock till our team can resolve the issue.

    CRT's only update, 19 December 2025.

  9. Nell Bridge Lock No 32 Cherwell

    Oxford CanalLondon and South East

    2 days

    From 23 March 2026

    Reopened 25 March 2026

    Where
    Lock 32, Nell Bridge Lock
    CRT reason
    Repair
    Cause
    Cause not stated
    Asset
    Lock

    Please be advised that this lock is currently closed due to a blocked by-weir-channel.. Our team are working hard to clear this as quickly as possible. We'll share an update as soon as we have more information. Thank you for your patience and understanding whilst we work to get…

    CRT's only update, 23 March 2026.

  10. Carpenter's Road Lock

    Old River LeaLondon and South East

    2 days

    From 5 April 2026

    Reopened 7 April 2026

    Where
    Lock 1a, Carpenter's Road Lock
    CRT reason
    Repair
    Cause
    Cause not stated
    Asset
    Lock

    Complete loss of power to Carpenter's Road Lock.

    CRT's only update, 5 April 2026.

  11. LN-016-005 - Lock 14, Ponders End Lock, East Side to LN-019-008 Lock 13, Enfield Loc

    Lee NavigationLondon and South East

    2 days

    From 11 July 2026

    Reopened 13 July 2026

    Where
    Lock 14, Ponders End Lock, East Side to Lock 13, Enfield Lock
    CRT reason
    Low Water Levels
    Cause
    Cause not stated
    Asset
    Canal or river

    Low water between Ponders End Lock and Enfield Lock on the Lea navigation has resulted in boats grounding. To allow pound level to recover, Ponders End Lock and Enfield Lock will be closed until levels stabilise and the level can be sustained. Causes for the low water levels are…

    CRT's only update, 11 July 2026.

  12. Marsworth Flight closed to Navigation. Lock 45 is closed and no navigation is possible above lock 43

    Grand Union CanalLondon and South East

    1 day

    From 7 May 2025

    Reopened 8 May 2025

    Where
    Lock 43 to Lock 45
    CRT reason
    Repair
    Cause
    Cause not stated
    Asset
    Lock

    The obstruction at lock 44 has now been cleared.

    Latest of 2 CRT updates, 8 May 2025.

  13. Navigation Closure - Oxford Canal, LK 39 Pidgeon's Lock , Kirtlington

    Oxford CanalLondon and South East

    1 day

    From 22 July 2025

    Reopened 23 July 2025

    Where
    Lock 39, Pigeons Lock
    CRT reason
    Underwater Obstruction
    Cause
    Cause not stated
    Asset
    Lock

    A full lock dewatering is required for our specialist contractors to access and if possible clear an obstruction from the Off Side Ground paddle culvert, we will also take this opportunity to survey the Tow path ground paddle culvert with CCTV, inspect and refurbish all lock and…

    CRT's only update, 7 July 2025.

  14. Lock 40, Wilmcote Top Lock

    South Stratford CanalWest Midlands

    1 day

    From 5 August 2025

    Reopened 6 August 2025

    Where
    Lock 40, Wilmcote Top Lock
    CRT reason
    Underwater Obstruction
    Cause
    Cause not stated
    Asset
    Lock

    An underwater obstruction has been identified within the lock chamber. Although the emergency response team attended site and attempted to remove it, the size and nature of the obstruction prevented them from making the lock safe. This obstruction is currently causing boats to…

    CRT's only update, 5 August 2025.

  15. Lock 27 Ebstree Lock, Staffs and Worcester Canal

    Staffordshire & Worcestershire CnlWest Midlands

    1 day

    From 15 November 2025

    Reopened 16 November 2025

    Where
    Lock 27 Ebstree Lock
    CRT reason
    Emergency Services Incident
    Cause
    Cause not stated
    Asset
    Lock

    High voltage electricity Cables down across Lock. DO NOT APPROACH AS MAY STILL BE LIVE. Keep at least 50 metres back. Police and National Grid informed. Team on route to close towpath.

    CRT's only update, 15 November 2025.

  16. Pound between Greens Lock 68 and Potters Lock 69

    Erewash CanalEast Midlands

    1 day

    From 30 April 2026

    Reopened 1 May 2026

    Where
    Lock 69 - Potters Lock to Lock 68 - Greens Lock
    CRT reason
    Maintenance
    Cause
    Cause not stated
    Asset
    Canal or river

    The navigation will be closed between Greens Lock 68 and Potters Lock 69 on the Erewash Canal on Thursday 30th April for emergency works. Please do not navigate this stretch during this time. We hope to finish by 4pm and will update this notice when the works are complete.

    CRT's only update, 29 April 2026.

  17. Lock 60 Crofton Lock - Lock 54 Cadley Lock

    Kennet & Avon CanalWales and South West

    1 day

    From 27 June 2026

    Reopened 28 June 2026

    Where
    Lock 60, Crofton Lock to Lock 54, Cadley Lock
    CRT reason
    Low Water Levels
    Cause
    Cause not stated
    Asset
    Canal or river

    Please be aware that due to a drained pound there is insufficient water on the summit pound to support navigation. This closure will allow time for the summit pound levels to rise and we expect navigation to be re-opened at the usual time tomorrow (Sunday 28th June) morning. We…

    CRT's only update, 27 June 2026.

  18. Salterhebble middle basin

    Calder & Hebble NavigationYorkshire and North East

    1 day

    From 28 June 2026

    Reopened 29 June 2026

    Where
    Lock 2, Salterhebble Middle
    CRT reason
    Low Water Levels
    Cause
    Cause not stated
    Asset
    Canal or river

    Levels have dropped overnight but is now being topped up throughout the day

    CRT's only update, 28 June 2026.

  19. 400 Metres south of Kinver Lock

    Staffordshire & Worcestershire CnlWest Midlands

    same day

    From 2 December 2025

    Reopened 2 December 2025

    Where
    Bridge 28 Whittington Horse Bridge to Lock 11 Kinver Lock
    CRT reason
    Repair
    Cause
    Cause not stated
    Asset
    Canal or river

    Please be advised that a service cable has fallen across the canal and towpath, obstructing navigation approximately 400 metres south of Kinver Lock. Our contractors have been informed and will attend as soon as possible. A further update will be issued once we have an estimated…

    CRT's only update, 2 December 2025.

  20. Between Lock 12 Commercial Road and Lock 11 Salmons Lane

    Regent's CanalLondon and South East

    same day

    From 5 February 2026

    Reopened 5 February 2026

    Where
    Lock 11, Salmons Lane Lock to Lock 12, Commercial Road Lock
    CRT reason
    Maintenance
    Cause
    Cause not stated
    Asset
    Canal or river

    Obstruction blocking canal has developed overnight. Operational colleagues are attending and rectifying this morning. Use alternative route via Hertford Union.

    CRT's only update, 5 February 2026.

  21. Kidlington Green Lock No 43, Lock Crescent, Kidlington

    Oxford CanalLondon and South East

    same day

    From 30 April 2026

    Reopened 30 April 2026

    Where
    Lock 43, Kidlington Green Lock
    CRT reason
    Underwater Obstruction
    Cause
    Cause not stated
    Asset
    Lock

    Please be advised that our operational team has identified an obstruction within the Towpath Ground Paddle culvert, which is currently affecting the lock's ability to fill for navigation. To resolve this, a top stop plank installation will be required so the lock head can be…

    CRT's only update, 27 April 2026.

  22. Lock 15 Marple

    Peak Forest CanalNorth West

    same day

    From 1 July 2026

    Reopened 1 July 2026

    Where
    Lock 15
    CRT reason
    Underwater Obstruction
    Cause
    Cause not stated
    Asset
    Lock

    Navigation is currently closed at Lock 15 on the Marple Flight on Peak Forest Canal due to an obstruction in the lock chamber. The team are currently on site to remove the obstruction, and the flight will be back open at 5pm. A further update will be provided today on or before…

    CRT's only update, 1 July 2026.