The archive / Bridgwater & Taunton Canal
Albert Street Cutting. Bridgwater & Taunton Canal
A navigation closure on the Bridgwater & Taunton Canal, 12 November 2021 to 11 July 2025 — 1,337 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Bridgwater & Taunton Canal
- Region
- Wales and South West
- Started
- 12 November 2021
- Status
- Reopened 11 July 2025
- Days shut
- 1,337
- CRT reason
- Repair
- Cause
- Cause not stated
- Asset
- Unspecified
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
What CRT said it was for
works complete
Where
- Bridgwater & Taunton Canal: Bridge 1, Victoria Rd to Bridge 4, Albert St
Updates · 1
71 days with no update after the last one.
1 May 2025 · 1,266 days since the previous
Please be advised that following planned inspection works through Albert Street Cutting the Trust has taken the decision to close the towpath and navigation with immediate effect in the interest of public safety. We are working with colleagues to ensure that remedial work to enable us to safely re-open the towpath and navigation is carried out as soon as possible. In the meantime, we apologise for any inconvenience & invite customers to contact the Customer Service Team on 03030404040 or at [enquiries.walessouthwest@canalrivertrust.org.uk](mailto:enquiries.walessouthwest@canalrivertrust.org.uk) should there be any specific questions regarding this notice.
Cite this: Canal closures, “Albert Street Cutting. Bridgwater & Taunton Canal”, https://crt-stoppages.pages.dev/notice/01968bb4-51d7-7a31-9ad0-c7b9ae32e935.