CRT Stoppages Archive

Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.

All closures / What fails / Culvert

Culvert

Too few unplanned closures of this kind in June to August 2026 and the same months a year earlier to tell a change from luck: 2 against 2. How this is tested.

On record
11 notices since May 2025: 9 closures, 1 restriction and 1 not yet started

In force today

2 closures of this kind are in force today, longest shut first. Filter the explorer to them.

Shut today, counted to today.
CanalWhereSinceDays shut
Rochdale CanalLock 81 Butler Street to Lock 83 Brownsfield31 March 2026179
Llangollen CanalLock 1, Swanley Lock to Lock 1, Baddiley Lock6 August 202651

By canal

7 canals have had a closure of this kind. A closure naming two canals counts on both.

Closures of this kind on each canal since May 2025, most first.
CanalClosures
Llangollen Canal4
Shropshire Union Canal2
Coventry Canal1
Huddersfield Broad Canal1
Huddersfield Narrow Canal1
Peak Forest Canal1
Rochdale Canal1

Every closure on record

Showing 9 closures and 1 restriction involving a culvert.

Period

Rank by

Population

Status

Duration

Cause

Asset affected

CRT reason

Region

9
closures
534
closure-days since May 2025
346
in cruising season
2
no reopening date
What these figures mean
Population
Which closures a figure counts. All closures is everything; Unplanned closure drops the works CRT flags as its winter programme and any day outside the cruising season (the Friday nearest 15 March to the Sunday before the first Monday in November). Scheduled work CRT does not flag as winter works still counts here. CRT Planned closure is the flagged winter programme alone.
Defensible duration
The days between a closure's start and its reopening date, counted only where the dates allow it. A cancelled notice, or one whose reopening precedes its start, has no defensible duration and is in no total.
Closure-days
One day on which one closure was in force. Two closures on the same day are two closure-days; where the question is how long a canal was actually disrupted, overlapping notices are unioned into single intervals. They are counted from 1 May 2025, when this archive begins: a closure that started earlier adds only its days since then, though its own row shows its whole length. Every figure and chart counts only the days inside the Period chosen above them.
In force
A closure is in a Period, and a day is one a closure affected, if it was in force at any time that day, including the morning it reopened. Closure-days measure how long, so they count whole days and not the reopening day: a closure can be in a Period and add no closure-day to it.

Closures in force each month

closures active during the month
0
1
1
1
1
1
2
1
2
2
3
1
2
1
1
3
2
May 25Jun 25Jul 25Aug 25Sep 25Oct 25Nov 25Dec 25Jan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26

Canals ranked by the season's closures

share of the period's cruising-season days up to today — a closure somewhere on a long canal is likelier, and does not mean the canal was impassableclosures in force on the period's cruising-season days — a longer canal has more to go wrong on

Where

closure-days by regionclosures by region

A region with more canal has more to go wrong on, so these totals partly measure its size. Regions compared by length of canal are on the Reliability page.

What causes them

closure-days by causeclosures by cause

CRT's reason

closure-days by the reason CRT filedclosures by the reason CRT filed

What fails on a lock

closure-days by part — unplanned lock failures naming a partclosures by part — unplanned lock failures naming a part

How long they last

closures by full length, including any days before May 2025 — the bands are not equal in width
2
1
1
2
3
0
<=1d2-7d8-30d31-90d91-365d>365d
10 results · every closure involving a culvertJump to list

Closures

  1. Lock 83 to Lock 81, Rochdale Canal

    Rochdale CanalNorth West

    179 days

    From 31 March 2026

    No reopening date

    Still shut

    Where
    Lock 81 Butler Street to Lock 83 Brownsfield
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    Since out last update contractors have encountered some unforeseen ground conditions during the excavation works which requires additional engineering assessments to be carried out. Work has now been scheduled to continue on Monday 14 September. Despite this short delay, work on…

    Latest of 16 CRT updates, 9 September 2026. 17 days without another.

  2. Bridge 131, Knolles Bridge to Bridge 133, Backford Bridge

    Shropshire Union CanalNorth West

    127 days

    From 17 July 2025

    Reopened 21 November 2025

    Where
    Bridge 133, Backford to Bridge 131, Knolles
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    We are pleased to confirm that the refilling and testing, originally scheduled to begin during the week commencing 24th November, will now be brought forward and will start on Thursday this week. Subject to successful testing and no unforeseen issues, we expect to reopen the…

    Latest of 13 CRT updates, 18 November 2025.

  3. Culvert 16, between bridges 22 and 23, Strines

    Peak Forest CanalNorth West

    106 days

    Fully shut 106 of CRT's 114 days

    From 27 October 2025

    Reopened 18 February 2026

    Where
    Bridge 22, Turf Lea Lift Bridge to Bridge 23, Stanley Hall Bridge
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    Due to time lost because of poor weather, this stoppage has been extended. Rewatering of the canal will take place on 12 and 13 February, followed by the removal of dams and the overpumping equipment. We currently expect the canal to reopen to boaters on 17 February, with the…

    Latest of 7 CRT updates, 12 February 2026.

  4. Culvert 15A, near Sutton Road Bridge in the Bonehill area of Tamworth

    Coventry CanalWest Midlands

    53 days

    From 19 January 2026

    Reopened 13 March 2026

    Where
    Sutton Road Bridge to A5 Road Bridge
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    Following an onsite review, we're now confident that the works can be completed within a shorter stoppage window. The revised stoppage dates are 19 January to 13 March.

    Latest of 2 CRT updates, 19 December 2025.

  5. Lock 1 Baddiley Lock to Lock 1 Swanley lock on the Llangollen Canal

    Llangollen CanalNorth West

    51 days

    From 6 August 2026

    No reopening date

    Still shut

    Where
    Lock 1, Swanley Lock to Lock 1, Baddiley Lock
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    Since our last update the fallen tree has now been removed, and our contractors are carrying out excavation works to gain access to the culvert. This will enable the team to undertake detailed inspections and surveys, providing the information required for our design engineers…

    Latest of 6 CRT updates, 18 September 2026. 8 days without another.

  6. Culvert 16, between locks 2 & 3 Baddiley; near Nantwich

    Llangollen CanalNorth West

    11 days

    From 2 March 2026

    Reopened 13 March 2026

    Where
    Lock 2, Baddiley Lock to Lock 3, Baddiley Lock
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    A stoppage is required to allow us to undertake repairs to Culvert 16. The closure will be in place between Locks 2 and 3 at Baddiley so that our teams can carry out the works safely. Thank you for your patience and understanding while we complete these essential repairs.

    CRT's only update, 12 February 2026.

  7. Lock 1 West to Lock 32 West

    Huddersfield Narrow CanalNorth West

    5 days

    From 13 August 2026

    Reopened 18 August 2026

    Where
    Lock 32 West to Lock 1 West
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    Please be advised navigation is currently closed between Lock 1 West and Lock 32 West on the Huddersfield Narrow Canal due to a leak flowing into a culvert between Lock 12 West and Lock 13 West in Micklehurst causing low water levels. Our local team are on site investigating the…

    CRT's only update, 13 August 2026.

  8. LA-007-004

    Llangollen CanalNorth West

    1 day

    From 22 June 2025

    Reopened 23 June 2025

    Where
    Stoneley Green Winding Hole to Thomasons Winding Hole
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    Due to a possible culvert collapse concern on culvert 16 LA-007-004 Llangollen canal, the canal is being close off to stop any further impact damage from the boats that are travelling over it. We will have a further update on 23/6/25.

    CRT's only update, 22 June 2025.

  9. Navigation Restriction - Huddersfield Broad Canal, Between lock 8 and Lock 9, Fartown - Culvert repairs completed at 2pm today - navigation reopen 2pm onwards.

    Huddersfield Broad CanalYorkshire and North East

    1 day

    From 20 May 2026

    Reopened 21 May 2026

    Where
    Lock 9, Red Doles Lock to Lock 8, Falls Lock
    CRT reason
    Maintenance
    Cause
    Broke, cause not given
    Asset
    Culvert

    The Culvert repairs are currently underway and shall be completed by 2pm. The navigation will be open from 2pm onwards.

    Latest of 2 CRT updates, 21 May 2026.

  10. Canal leak into Culvert 68, below Bridge 69, Peters Bridge, Lower Frankton, Ellesmere

    Llangollen CanalWest Midlands

    7 days

    From 17 August 2026

    Ended 24 August 2026

    Restriction, not a full closure

    Where
    Culvert 68 to Bridge 69, Peters Bridge
    CRT reason
    Repair
    Cause
    Broke, cause not given
    Asset
    Culvert

    We are carrying out repair works to investigate and address a leak between the canal and an adjacent culvert. These works are necessary to protect the canal infrastructure and maintain the waterway. To facilitate the works, a horseshoe cofferdam will be installed within the…

    CRT's only update, 13 August 2026.

Coming up

Scheduled but not yet started, so in no figure above.

1 scheduled.
ClosureFromPlanned
Culvert 49, near Bridge 92, Nantwich Junction Bridge
Shropshire Union Canal · Repair
4 January 202767 days

What fails · Canals · Reliability · Trends · Download data