The archive / Coventry Canal

Culvert 15A, near Sutton Road Bridge in the Bonehill area of Tamworth

A navigation closure on the Coventry Canal, 19 January 2026 to 13 March 2026 — 53 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Coventry Canal
Region
West Midlands
Started
19 January 2026
Status
Reopened 13 March 2026
Days shut
53
CRT reason
Repair
Cause
Wear and tear
Asset
Culvert

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 2

84 days with no update after the last one.

19 December 2025 · 173 days since the previous

Following an onsite review, we're now confident that the works can be completed within a shorter stoppage window. The revised stoppage dates are 19 January to 13 March.

29 June 2025 · 0 days since the previous

Culvert 15A that runs under the Coventry Canal requires repair works, including repairing the upstream headwall, and re-lining the culvert with a 'cured-in-place' pipe liner. The works will also involve undertaking canal bed repairs over the top of the culvert requiring the dewatering of this section of the canal.

Cite this: Canal closures, “Culvert 15A, near Sutton Road Bridge in the Bonehill area of Tamworth”, https://crt-stoppages.pages.dev/notice/0197bdb6-fdc1-7305-b3a1-541d9759bd82.