CRT Stoppages Archive

Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.

All closures / What fails / Weir

Weir

No unplanned closure of this kind can yet be set beside a year earlier. How this is tested.

On record
3 notices since May 2025: 2 closures and 1 not yet started

In force today

No closure of this kind is in force today.

By canal

3 canals have had a closure of this kind. A closure naming two canals counts on both.

Closures of this kind on each canal since May 2025, most first.
CanalClosures
Macclesfield Canal1
Monmouthshire & Brecon Canal1
River Stort1

Every closure on record

Showing 2 closures involving a weir.

Period

Rank by

Population

1 closure is in neither group: 1 unplanned with no day in the cruising season since May 2025.

Status

Duration

Cause

Asset affected

CRT reason

Region

2
closures
12
closure-days since May 2025
11
in cruising season
0
no reopening date
What these figures mean
Population
Which closures a figure counts. All closures is everything; Unplanned closure drops the works CRT flags as its winter programme and any day outside the cruising season (the Friday nearest 15 March to the Sunday before the first Monday in November). Scheduled work CRT does not flag as winter works still counts here. CRT Planned closure is the flagged winter programme alone.
Defensible duration
The days between a closure's start and its reopening date, counted only where the dates allow it. A cancelled notice, or one whose reopening precedes its start, has no defensible duration and is in no total.
Closure-days
One day on which one closure was in force. Two closures on the same day are two closure-days; where the question is how long a canal was actually disrupted, overlapping notices are unioned into single intervals. They are counted from 1 May 2025, when this archive begins: a closure that started earlier adds only its days since then, though its own row shows its whole length. Every figure and chart counts only the days inside the Period chosen above them.
In force
A closure is in a Period, and a day is one a closure affected, if it was in force at any time that day, including the morning it reopened. Closure-days measure how long, so they count whole days and not the reopening day: a closure can be in a Period and add no closure-day to it.

Closures in force each month

closures active during the month
0
0
0
0
0
1
0
0
1
0
0
0
0
0
0
0
0
May 25Jun 25Jul 25Aug 25Sep 25Oct 25Nov 25Dec 25Jan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26

Canals ranked by the season's closures

share of the period's cruising-season days up to today — a closure somewhere on a long canal is likelier, and does not mean the canal was impassableclosures in force on the period's cruising-season days — a longer canal has more to go wrong on

Where

closure-days by regionclosures by region

A region with more canal has more to go wrong on, so these totals partly measure its size. Regions compared by length of canal are on the Reliability page.

What causes them

closure-days by causeclosures by cause
Other cause11
Other cause11

CRT's reason

closure-days by the reason CRT filedclosures by the reason CRT filed

What fails on a lock

closure-days by part — unplanned lock failures naming a partclosures by part — unplanned lock failures naming a part

How long they last

closures by full length, including any days before May 2025 — the bands are not equal in width
1
0
1
0
0
0
<=1d2-7d8-30d31-90d91-365d>365d
2 results · every closure involving a weirJump to list

Closures

  1. Lock 7, Bosley weir

    Macclesfield CanalNorth West

    11 days

    From 6 October 2025

    Reopened 17 October 2025

    Where
    Bosley Lock 1 to Bosley Lock 12
    CRT reason
    Repair
    Cause
    Planned works
    Asset
    Weir

    With a shorter window for the lock gate works at Bosley Lock 7 to allow a window for boat passage – we will undertake improvements to the weir at Lock 7 from 6 October to 17 October while there are other closures in place. We were awaiting listed building consent but now have…

    CRT's only update, 3 October 2025.

  2. Fixed Weir 9 66m W of Bridge 21

    River StortLondon and South East

    1 day

    From 16 January 2026

    Reopened 17 January 2026

    Where
    Lock 9, Latton Lock to Bridge 21, Harlow Footbridge
    CRT reason
    Boating Incident
    Cause
    Other cause
    Asset
    Weir

    The craft has been successfully removed from the weir - Unfortunately due to a blocked paddle at Latton Lock, the navigation will remain closed until Saturday when the duty team can attend to clear the obstruction - An update will be published once the navigation is open

    Latest of 2 CRT updates, 16 January 2026.

Coming up

Scheduled but not yet started, so in no figure above.

1 scheduled.
ClosureFromPlanned
Weir 2A, Llanfrynach weir
Monmouthshire & Brecon Canal · Repair
2 November 202646 days

What fails · Canals · Reliability · Trends · Download data