Weir 2A, Llanfrynach weir
Scheduled: 2 November 2026 to 18 December 2026 (46 days planned), on the Monmouthshire & Brecon Canal. It has not started, so it is in no figure — see the archive's Coming up list.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Monmouthshire & Brecon Canal
- Region
- Wales and South West
- Started
- 2 November 2026
- Status
- Scheduled
- Days planned
- 46
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Weir
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Monmouthshire & Brecon Canal: Weir 2A, Llanfrynach Weir to Weir 2A, Llanfrynach Weir
Updates · 1
49 days with no update after the last one.
4 August 2026 · 0 days since the previous
A navigation and towpath closure is required to carry out reinstatement of the weir structure