Weir 2A, Llanfrynach weir

Scheduled: 2 November 2026 to 18 December 2026 (46 days planned), on the Monmouthshire & Brecon Canal. It has not started, so it is in no figure — see the archive's Coming up list.

Source: this notice on canalrivertrust.org.uk

Waterway
Monmouthshire & Brecon Canal
Region
Wales and South West
Started
2 November 2026
Status
Scheduled
Days planned
46
CRT reason
Repair
Cause
Wear and tear
Asset
Weir

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

49 days with no update after the last one.

4 August 2026 · 0 days since the previous

A navigation and towpath closure is required to carry out reinstatement of the weir structure