The archive / Macclesfield Canal

Lock 7, Bosley weir

A navigation closure on the Macclesfield Canal, 6 October 2025 to 17 October 2025 — 11 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Macclesfield Canal
Region
North West
Started
6 October 2025
Status
Reopened 17 October 2025
Days shut
11
CRT reason
Repair
Cause
Nothing failed
Asset
Weir

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

14 days with no update after the last one.

3 October 2025 · 0 days since the previous

With a shorter window for the lock gate works at Bosley Lock 7 to allow a window for boat passage – we will undertake improvements to the weir at Lock 7 from 6 October to 17 October while there are other closures in place. We were awaiting listed building consent but now have the permissions we need. Apologies for the short notice but this is the best way that we can both get the works done where needed and create the opportunities for passage ahead of the winter.