Something was shut here on 12% of this cruising season — 28 of its 231 days — across 11 separate closures.
That means a closure somewhere on the canal, not that the whole canal was impassable. Every closure below names the locks or bridges it sat between.
1 closure is still shut now, and 1 of those has no reopening date. Filter to it.
- Regions
- Yorkshire and North East
- On record
- 17 closures
The season, closure by closure
Each row is one closure. A bar starts and ends where the closure did, and its length is how long it ran; dashed bars have not started yet.
Every closure on record
Showing all 17 closures on the New Junction Canal.
17
closures
146
closure-days
21
in cruising season
1
no reopening date
What these figures mean
- Population
- Which closures a figure counts. All closures is everything; Unplanned, in season drops CRT's scheduled winter programme and any day outside the 15 March to 31 October cruising season; CRT winter programme is that maintenance alone.
- Defensible duration
- The days between a closure's start and its reopening date, counted only where the dates allow it. A cancelled notice, or one whose reopening precedes its start, has no defensible duration and is in no total.
- Closure-days
- One day on which one closure was in force. Two closures on the same day are two closure-days; where the question is how long a canal was actually disrupted, overlapping notices are unioned into single intervals.
May 25Jun 25Jul 25Aug 25Sep 25Oct 25Nov 25Dec 25Jan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26
Showing the 17 longest of 17. Every row links to the notice CRT published.