Lock 25, Bottom Lock
Scheduled: 16 November 2026 to 27 November 2026 (11 days planned), on the Leeds & Liverpool Canal. It has not started, so it is in no figure — see the archive's Coming up list.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Leeds & Liverpool Canal
- Region
- North West
- Started
- 16 November 2026
- Status
- Scheduled
- Days planned
- 11
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Lock
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Leeds & Liverpool Canal: Lock 25, Bingley 5 Rise Bottom Lock to Lock 25, Bingley 5 Rise Bottom Lock
Updates · 1
49 days with no update after the last one.
4 August 2026 · 0 days since the previous
A navigation closure is required to carry out grouting works to the lock