Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.
The archive / Hertford Union Canal
Navigation Closure - Hertford Union Canal, Top Lock, Lock 1 - Bottom Lock, Lock 3, Bow/Hackney Wick
A navigation closure on the Hertford Union Canal, started 30 July 2026 — still shut after 54 days. No reopening date is published.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Hertford Union Canal
- Region
- London and South East
- Started
- 30 July 2026
- Status
- Still shut
- Days shut
- 54
- CRT reason
- Low Water Levels
- Cause
- Cause not stated
- Asset
- Canal or river
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Hertford Union Canal: Lock 1, Top Lock to Lock 3, Bottom Lock
Updates · 4
34 days with no update after the last one.
19 August 2026 · 15 days since the previous
Please be advised that due to the continued low water levels, the Hertford Union Canal closure has been extended. This is to help our ongoing efforts to manage the water levels across the wider network and to maintain navigational Safety. The situation will be reviewed on Thursday, 24 September and a further update will be provided at that time. We appreciate your continued patience and understanding during this period.
4 August 2026 · 1 days since the previous
Please be advised that due to the continued low water levels, the Hertford Union Canal closure has been extended. The situation will be reviewed on Friday, 21 August and a further update will be provided at that time. We appreciate your continued patience and understanding during this period.
Earlier updates · 2
3 August 2026 · 5 days since the previous
Please be advised due to the continued low water levels, we have extended the closure on the Hertford Union Canal. We will review this on Wednesday 5th August. We appreciate your continued patience and understanding during this time.
29 July 2026 · 0 days since the previous
As part of our ongoing efforts to manage and recover water levels across the wider network, a navigation closure is necessary on the Hertford Union Canal between Top Lock, Lock 1 and Bottom Lock, Lock 3 on the Hertford Union Canal. Whilst we understand that closures can be disruptive, this action is being taken to help safeguard the network and support future navigation. We will close the navigation at 15:00 on Thursday 30th July and we will review the navigation conditions on Monday 3rd August and provide a further update. We appreciate your patience and understanding during this time.
Cite this: Canal closures, “Navigation Closure - Hertford Union Canal, Top Lock, Lock 1 - Bottom Lock, Lock 3, Bow/Hackney Wick”, https://crt-stoppages.pages.dev/notice/019fad35-1cef-7aaa-95e4-a72a783ace13.
Every closure on Hertford Union Canal · Download the data · Method and limits