Lock 1 to Lock 16 Marple Flight

A navigation closure on the Peak Forest Canal, 9 June 2026 to 29 June 2026 — 20 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Peak Forest Canal
Region
North West
Started
9 June 2026
Status
Reopened 29 June 2026
Days shut
20
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

What CRT said it was for

Following the successful replacement to the damaged balance beam at Lock 10 on the Peak Forest Canal, navigation has now resumed. We would like to thank all boaters for their patience and understanding.

Where

Updates · 5

6 days with no update after the last one.

23 June 2026 · 1 days since the previous

We have now established a method of repair for the damaged balance beam at Lock 10 on the Peak Forest Canal. The team will be on site from 8:00 am on Monday 29 June to carry out the replacement of the balance beam. We currently anticipate that the works will be completed on the same day. Whilst these works are being undertaken, the Marple Flight will remain closed to navigation, and the towpath will also be closed between Locks 9 and 12 for the duration of the works to ensure the safety of both our workforce and the public. A further update will be provided on Monday 29 June.

22 June 2026 · 4 days since the previous

Navigation remains closed between Locks 1 and 16 on the Marple Flight due to damage to the balance beam at Lock 10. Our team and contractors have been on site to finalising the method of repair and we anticipate they will be on site this week with a crane to install the new beam .  A further update  will be provided on or before Thursday 25th June

Earlier updates · 3

18 June 2026 · 7 days since the previous

Navigation remains closed between Locks 1 and 16 on the Marple Flight following damage to the balance beam at Lock 10. We have sourced the balance beam, which has now been reshaped, and our reactive team is currently planning the repair works. They are currently liaising with our specialist contractors to arrange attendance and complete the installation. We apologise for any inconvenience caused and thank you for your patience while these works are carried out. The next update will be provided on or before Monday 22 June 2026.

11 June 2026 · 2 days since the previous

Navigation remains closed between Locks 1 and 16 on the Marple Flight of the Peak Forest Canal following damage to the balance beam at Lock 10. Our reactive team has completed the necessary inspections and confirmed that the balance beam requires replacement. A suitable replacement beam has now been sourced however, it will need to be reshaped before repair works can be scheduled and carried out. The beam is being transported to the workshop and is expected to take approximately three days to reshape. Once the reshaping is complete, the team will be able to schedule and install the replacement. The next update will be provided on or before Thursday 18 June.

9 June 2026 · 0 days since the previous

Navigation is currently closed between Locks 1 and 16 on the Marple Flight, Peak Forest Canal, following damage to the balance beam on the lock gate at Lock 10. Our teams have attended site today and carried out initial inspections and further inspection will be continued tomorrow.  A further update will be provided on or before Thursday 11 June.