Navigation Closure - Lee Navigation, Lock 8, Aqueduct Lock, Broxbourne
A navigation closure on the Lee Navigation, 10 April 2026 to 14 April 2026 — 4 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Lee Navigation
- Region
- London and South East
- Started
- 10 April 2026
- Status
- Reopened 14 April 2026
- Days shut
- 4
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Lock
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
What CRT said it was for
The lock has been repaired and the navigation has reopened.
Where
- Lee Navigation: Lock 8, Aqueduct Lock to Lock 8, Aqueduct Lock
Updates · 2
4 days with no update after the last one.
10 April 2026 · 0 days since the previous
Please be advised the paddle and rod are missing from the lower towpath side. A new paddle and bolts planned to be fitted next week.
10 April 2026 · 0 days since the previous
Paddle off rod and missing from lower towpath side. New paddle required and bolts with boat onsite to refit.
Cite this: Canal closures, “Navigation Closure - Lee Navigation, Lock 8, Aqueduct Lock, Broxbourne”, https://crt-stoppages.pages.dev/notice/019d777e-c616-7e6b-9095-aad2b5f9fb36.
Every closure on Lee Navigation · Download the data · Method and limits