Canal closures

Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.

The archive / Llangollen Canal

Lock 1, New Marton, above Welsh Frankton

A navigation closure on the Llangollen Canal, 9 February 2026 to 27 February 2026 — 18 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Llangollen Canal
Region
West Midlands
Started
9 February 2026
Status
Reopened 27 February 2026
Days shut
18
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

31 days with no update after the last one.

27 January 2026 · 0 days since the previous

We need to introduce an emergency stoppage at Lock 1, New Marton, above Welsh Frankton, on the Llangollen Canal to allow essential repair works to be carried out. The bottom gate has developed a serious water leak, which is preventing the lock from filling correctly. Repairs are required to the lock gates and cill, along with associated brickwork restoration. Given the impact on boats currently within the now‑isolated length of canal, we are keen to undertake these repairs now, ahead of the main boating season, to minimise longer‑term disruption. The stoppage will be in place from 9 February until 27 February. We apologise for any inconvenience this may cause and thank you for your understanding while we complete these vital works.