Canal closures

Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.

The archive / Peak Forest Canal

Sluice 1 - Dukinfield, Tameside

A navigation closure on the Peak Forest Canal, 9 February 2026 to 27 February 2026 — 18 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Peak Forest Canal
Region
North West
Started
9 February 2026
Status
Reopened 27 February 2026
Days shut
18
CRT reason
Repair
Cause
Wear and tear
Asset
Sluice

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

49 days with no update after the last one.

9 January 2026 · 0 days since the previous

Following a recent survey of the sluice, we have identified that the paddle has become detached and the existing chamber stop planks have deteriorated. To safely replace these components, a stoppage is required. While the canal is dewatered, we will also use a jet vac tanker to remove silt from in front of the sluice inlet. This will help ensure the sluice can operate effectively for flood management and continue to protect nearby critical assets.  This stoppage will run from 9 February to 27 February. Please note that the towpath will be restricted during these works. Towpath users may be asked to wait briefly while the site is made safe for passage. Thank you for your understanding while we carry out these essential works.