Fishpond Lock

A navigation closure on the Aire & Calder Navigation Main Line, 5 January 2026 to 9 January 2026 — 4 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Aire & Calder Navigation Main Line
Region
Yorkshire and North East
Started
5 January 2026
Status
Reopened 9 January 2026
Days shut
4
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 2

17 days with no update after the last one.

23 December 2025 · 0 days since the previous

Please note, the completion time for works at Fishpond Lock has been revised to 17:00 on Friday 9th January.

23 December 2025 · 0 days since the previous

Please be aware that Fishpond Lock will be closed to allow divers access to inspect and repair the damaged sill.