Sutton Weaver Swing Bridge
A navigation closure on the Weaver Navigation, 8 December 2025 to 12 December 2025 — 4 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Weaver Navigation
- Region
- North West
- Started
- 8 December 2025
- Status
- Reopened 12 December 2025
- Days shut
- 4
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Swing bridge
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Weaver Navigation: Elsan, Sutton Weaver Swing Bridge to Elsan, Sutton Weaver Swing Bridge
Updates · 2
0 days with no update after the last one.
12 December 2025 · 24 days since the previous
We're pleased to inform you that works on site have been completed ahead of schedule, and the navigation will be open from 4pm today. Please note, the restriction in the area remains ongoing.
18 November 2025 · 0 days since the previous
As part of the ongoing repairs to Sutton Weaver Swing Bridge, currently being carried out under a restriction, a stoppage is required to install a power cable across the bed of the navigation using divers. To facilitate this, a stoppage will run from 8th December to 19th December.