The archive / Pocklington Canal
Lock 8, Gardam Lock - Near Melbourne
A navigation closure on the Pocklington Canal, 8 September 2025 to 10 October 2025 — 32 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Pocklington Canal
- Region
- Yorkshire and North East
- Started
- 8 September 2025
- Status
- Reopened 10 October 2025
- Days shut
- 32
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Lock
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Pocklington Canal: Swingbridge 7 to Lock 8, Gardam Lock
Updates · 3
7 days with no update after the last one.
3 October 2025 · 36 days since the previous
Unfortunately, this stoppage has been extended by a week. During the dismantling of the gates, components not originally scheduled for replacement were found to be in poor condition. This extension will allow our technicians to carry out a full assessment and formalise a solution. In the meantime, the onsite team is progressing with repairs to the lock cill, which was also found to be in poor condition during the dewatering process.
28 August 2025 · 112 days since the previous
Due to concerns over the likelihood of flooding at this lock in winter, the team have brought these works forward to September, taking advantage of the current canal closure at this location to minimise disruption.
8 May 2025 · 0 days since the previous
A navigation and towpath closure are required for top and bottom gate leakage repair works