Keadby Rail Drawbridge, Bridge 83
A navigation closure on the Stainforth & Keadby Canal, 7 May 2025 to 13 May 2025 — 6 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Stainforth & Keadby Canal
- Region
- Yorkshire and North East
- Started
- 7 May 2025
- Status
- Reopened 13 May 2025
- Days shut
- 6
- CRT reason
- Repair
- Cause
- Weather
- Asset
- Bridge
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
What CRT said it was for
Opened
Where
- Stainforth & Keadby Canal: Bridge 83, Keadby Rail Drawbridge to Bridge 83, Keadby Rail Drawbridge
Updates · 3
1 days with no update after the last one.
12 May 2025 · 5 days since the previous
Keadby Rail Drawbridge is still closed and the high temperatures are affecting the operating mechanisms. The bridge can operate once the temperature has dropped below 26 degrees and has stayed below for 12 hours. We will wait for an update from Network Rail once this condition has been reached and the bridge is safe to operate we will then update the notice to advise boaters.
7 May 2025 · 0 days since the previous
Further to the earlier notice, Keadby Rail Drawbridge, Bridge 83 is closed to boaters due to mechanical failure. Network Rail engineers are to attend on Saturday evening (10/05/2025) to make the repairs. This notice will be updated once we have an update from Network Rail.
7 May 2025 · 0 days since the previous
Vazons Swing Bridge is closed to boaters due to mechanical failure. Network Rail engineers are to attend on Saturday evening (10/05/2025) to make the repairs. This notice will be updated once we have an update from Network Rail.