The archive / Stainforth & Keadby Canal
Stainforth & Keadby Canal
3.2 closure-days per kilometre (95% range 2.5–4.0) — 79 days across 13 closures of this 24km canal.
Lengths from CRT's ArcGIS open data, published under the strictest reading of its licence. A notice is attributed to the whole named waterway, not to a point.
Something was shut here on 13% of this cruising season — 30 of its 231 days — across 5 separate closures.
That means a closure somewhere on the canal, not that the whole canal was impassable. Every closure below names the locks or bridges it sat between.
Nothing is shut on this canal today.
- Regions
- Yorkshire and North East
- On record
- 13 closures
The season, closure by closure
Each row is one closure. A bar starts and ends where the closure did, and its length is how long it ran; dashed bars have not started yet.
Every closure on record
Showing all 13 closures on the Stainforth & Keadby Canal.
What these figures mean
- Population
- Which closures a figure counts. All closures is everything; Unplanned, in season drops CRT's scheduled winter programme and any day outside the 15 March to 31 October cruising season; CRT winter programme is that maintenance alone.
- Defensible duration
- The days between a closure's start and its reopening date, counted only where the dates allow it. A cancelled notice, or one whose reopening precedes its start, has no defensible duration and is in no total.
- Closure-days
- One day on which one closure was in force. Two closures on the same day are two closure-days; where the question is how long a canal was actually disrupted, overlapping notices are unioned into single intervals.
| Notice | Extent | Started | Days |
|---|---|---|---|
| Navigation Closure - Stainforth & Keadby Canal, FK-024-003, Keadby - Reopened | Bridge 83, Keadby Rail Drawbridge | 2026-01-12 | 17 |
| Keadby Lock - closure | Keadby Lock | 2026-07-28 | 17 |
| Bridge 83, Keadby Rail Drawbridge | Bridge 83, Keadby Rail Drawbridge | 2025-10-31 | 10 |
| Keadby Rail Drawbridge - now operational | Bridge 83, Keadby Rail Drawbridge | 2025-11-17 | 9 |
| Keadby Rail Drawbridge, Bridge 83 | Bridge 83, Keadby Rail Drawbridge | 2025-05-07 | 6 |
| Bridge 83, Keadby Rail Drawbridge - now operational | Bridge 83, Keadby Rail Drawbridge | 2025-11-28 | 6 |
| Keadby Rail Drawbridge - operational | Bridge 83, Keadby Rail Drawbridge | 2026-04-10 | 5 |
| Keadby Rail Bridge | Bridge 83, Keadby Rail Drawbridge | 2025-11-13 | 4 |
| Navigation Closure - Stainforth & Keadby Canal, Medge Hall swing bridge, Crowle | Medgehall Swing Bridge | 2025-08-20 | 2 |
| Godnow Swnigbridge | Godnow Swing Bridge | 2026-05-30 | 2 |
| Keadby Rail Drawbridge - non-operational | Bridge 83, Keadby Rail Drawbridge | 2026-05-01 | 1 |
| Wykewell Lift Bridge & Moors Swing Bridge - Planned power outage | Wykewell Lift Bridge to Moores Swing Bridge | 2025-08-13 | same day |
| Keadby Rail Drawbridge - fixed | Bridge 83, Keadby Rail Drawbridge | 2026-04-20 | same day |
Showing the 13 longest of 13. Every row links to the notice CRT published.
Not counted
Cancelled notices and ones whose dates cannot be right are in no figure on this page. They are kept here because CRT published them.
| Notice | State | Started |
|---|---|---|
| Bridge 83, Keadby Rail Drawbridge | Cancelled | 1 June 2025 |