Quoisley Lock, near Marbury

A navigation closure on the Llangollen Canal, 5 January 2026 to 27 March 2026 — 81 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Llangollen Canal
Region
North West
Started
5 January 2026
Status
Reopened 27 March 2026
Days shut
81
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 2

25 days with no update after the last one.

2 March 2026 · 300 days since the previous

We wanted to let you know that the works at Quoisley Lock will require additional time to complete. During the dewatering of the lock, it was identified that the lock gates were in significantly worse condition than expected, making repair unfeasible. New gates are therefore being manufactured, and the works have changed from a repair to a full gate replacement. As additional time is required to fabricate the new gates and subsequently complete their installation on site, the works will need to be extended by a further two weeks and will now complete on 27 March. We apologise for any inconvenience caused and appreciate your understanding while we complete these essential works.

6 May 2025 · 0 days since the previous

A navigational closure is required for top gate heads and heals replacement.