Canal closures

Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.

The archive / Huddersfield Broad Canal

Lock 8 is non operational as replacing the footboard platform, offside tail paddle unable to be used.

A navigation closure on the Huddersfield Broad Canal, 7 September 2026 to 9 September 2026 — 2 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Huddersfield Broad Canal
Region
Yorkshire and North East
Started
7 September 2026
Status
Reopened 9 September 2026
Days shut
2
CRT reason
Repair
Cause
Struck by boat or vehicle
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

What CRT said it was for

Though the footboards have been removed, it is the downstream paddles that are not working, but the lock can still be operated using the towpath side paddle only.

Where

Updates · 2

1 days with no update after the last one.

8 September 2026 · 1 days since the previous

The footboards and elbows have been removed and taken to the Fabrications company to be repaired/remade. We will update the notice when further updates are received on the progress of the works.

7 September 2026 · 0 days since the previous

On inspection, it has been found that following a collision that the elbow holding the footboards have been significantly damaged and causes a hazard to users of the lock. The offside tail paddle is out of service whilst we get the footboard platform replaced. The reactive team will be carrying out the repairs in the week and we will update the notice on Friday 11th September, with the progression of the works

Cite this: Canal closures, “Lock 8 is non operational as replacing the footboard platform, offside tail paddle unable to be used.”, https://crt-stoppages.pages.dev/notice/01a07aff-7982-7c98-b6ed-688df5d12286.

Every closure on Huddersfield Broad Canal · Download the data · Method and limits