The archive / Oxford Canal

Bridge 128 Willison's Bridge, Wormleighton

Scheduled: 2 November 2026 to 12 March 2027 (130 days planned), on the Oxford Canal. It has not started, so it is in no figure — see the archive's Coming up list.

Source: this notice on canalrivertrust.org.uk

Waterway
Oxford Canal
Region
West Midlands
Started
2 November 2026
Status
Scheduled
Days planned
130
CRT reason
3rd Party Works
Cause
Nothing failed
Asset
Bridge

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

47 days with no update after the last one.

6 August 2026 · 0 days since the previous

Contractors working on behalf of High Speed 2 Limited plan to demolish an existing accommodation bridge ( Bridge 128 ) and construct a replacement new bridge over the canal. We are currently exploring whether opportunities may exist to provide temporary navigation openings during the works; however, this remains under review and cannot be guaranteed at this stage. Further updates will be provided as arrangements are confirmed.

Cite this: Canal closures, “Bridge 128 Willison's Bridge, Wormleighton”, https://crt-stoppages.pages.dev/notice/019fd725-0852-7387-9622-4872ac2db1b4.