The archive / Birmingham & Warwick Junction Cnl

Bridge 108F Saltley Underbridge ( High Speed 2 )

Scheduled: 2 November 2026 to 12 March 2027 (130 days planned), on the Birmingham & Warwick Junction Cnl. It has not started, so it is in no figure — see the archive's Coming up list.

Source: this notice on canalrivertrust.org.uk

Waterway
Birmingham & Warwick Junction Cnl
Region
West Midlands
Started
2 November 2026
Status
Scheduled
Days planned
130
CRT reason
3rd Party Works
Cause
Nothing failed
Asset
Bridge

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

47 days with no update after the last one.

6 August 2026 · 0 days since the previous

Contractors working on behalf of High Speed 2 Limited will be building two new viaducts over the Birmingham and Warwick Junction Canal. To undertake these works safely it will be necessary to close the canal and the canal towpath. We are currently exploring whether opportunities may exist to provide temporary navigation openings during the works; however, this remains under review and cannot be guaranteed at this stage. Further updates will be provided as arrangements are confirmed.

Cite this: Canal closures, “Bridge 108F Saltley Underbridge ( High Speed 2 )”, https://crt-stoppages.pages.dev/notice/019fd720-37bd-7a08-b353-217501918e38.