Bridge 31, Oblique Bridge, St Pancras, London

Scheduled: 29 January 2027 to 12 March 2027 (42 days planned), on the Regent's Canal. It has not started, so it is in no figure — see the archive's Coming up list.

Source: this notice on canalrivertrust.org.uk

Waterway
Regent's Canal
Region
London and South East
Started
29 January 2027
Status
Scheduled
Days planned
42
CRT reason
3rd Party Works
Cause
Nothing failed
Asset
Bridge

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

47 days with no update after the last one.

6 August 2026 · 0 days since the previous

Bridge contractors working on behalf of the developer Reef and Partners will require a full canal closure to install a new footbridge over the canal. The new footbridge will form a new pedestrian link between Granary Street and Camley Street.