Scheduled: 25 January 2027 to 5 February 2027 (11 days planned), on the Rufford Branch (L&L Canal). It has not started, so it is in no figure — see the archive's Coming up list.

Source: this notice on canalrivertrust.org.uk

Waterway
Rufford Branch (L&L Canal)
Region
North West
Started
25 January 2027
Status
Scheduled
Days planned
11
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

49 days with no update after the last one.

4 August 2026 · 0 days since the previous

A navigation closure is required to carry out grouting works to the lock