Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.
The archive / Kennet & Avon Canal
Lock 100 Sulhamstead Lock, Kennet & Avon Canal
A navigation closure on the Kennet & Avon Canal, 1 August 2026 to 10 September 2026 — 40 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Kennet & Avon Canal
- Region
- Wales and South West
- Started
- 1 August 2026
- Status
- Reopened 10 September 2026
- Days shut
- 40
- CRT reason
- Boating Incident
- Cause
- Wear and tear
- Asset
- Lock
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Kennet & Avon Canal: Lock 100, Sulhamstead Lock to Lock 100, Sulhamstead Lock
Updates · 9
0 days with no update after the last one.
10 September 2026 · 3 days since the previous
Further to the notice below, we are pleased to advise that the repair to Sulhamstead Lock has now been completed and the navigation is open. Thank you for your patience.
7 September 2026 · 4 days since the previous
Further to the notice below, please be advised that the contractors are expected to complete the current works during the afternoon of Wednesday 9th September. Subject to the successful completion of these works the canal will reopen on Thursday morning. We would like to thank customers for their patience and cooperation during this period of essential maintenance.
Earlier updates · 7
3 September 2026 · 2 days since the previous
Further to the notice below, we are pleased to advise that works at Sulhamstead are proceeding well. We have agreed with the contractors to temporarily reopen the lock from 4pm on Friday 4th September until 8am on Monday 7th September, allowing passage over the weekend. Thank you for your patience.
1 September 2026 · 11 days since the previous
Further to the notice below, please be advised that contractors have now started the repair works at Sulhamstead Lock. We will provide a further update later in the week as progress is made.
21 August 2026 · 4 days since the previous
Further to the notice below, please be advised that the works at Sulhamstead Lock have been delayed. Contractors will now be on site on Tuesday 1st September. We will provide further updates as the works progress. Thank you for your patience and understanding.
17 August 2026 · 13 days since the previous
Please be advised that works at Sulhamstead Lock 100 are scheduled to commence on Wednesday 26th August. The works are expected to take approximately one week to complete. We will provide further updates as the works progress. Thank you for your patience and understanding.
4 August 2026 · 1 days since the previous
Further to the notice below, we would like to advise our customers that our Engineers and Operations teams have attended site and confirmed that a replacement balance beam is required. Unfortunately, there is a significant lead time for a replacement beam to be manufactured and delivered. We are currently exploring alternative options and will provide further updates as soon as more information becomes available.
3 August 2026 · 2 days since the previous
Unfortunately, damage has occurred to the balance beam at Lock 100 (Sulhamstead Lock), resulting in the lock being temporarily inoperable. Our engineers are currently assessing the damage and investigating the cause. We will provide a further update as soon as more information becomes available. We apologise for any inconvenience caused and appreciate your patience while we work to resolve the issue.
1 August 2026 · 0 days since the previous
Unfortunately there has been some damage to the balance beam at Lock 100 Sulhamstead Lock which has made the lock inoperable. A further update will be provided on the morning of Monday 3rd August with a more specific timeline for repair.
Cite this: Canal closures, “Lock 100 Sulhamstead Lock, Kennet & Avon Canal”, https://crt-stoppages.pages.dev/notice/019fbd41-0fd2-7066-86a6-ed18c8013755.
Every closure on Kennet & Avon Canal · Download the data · Method and limits