Canal closures

Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.

The archive / Huddersfield Narrow Canal

Between Lk24 and LK8 - recovered and reopened

A navigation closure on the Huddersfield Narrow Canal, 6 June 2026 to 11 June 2026 — 5 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Huddersfield Narrow Canal
Region
Yorkshire and North East
Started
6 June 2026
Status
Reopened 11 June 2026
Days shut
5
CRT reason
Low Water Levels
Cause
Other cause
Asset
Canal or river

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 5

0 days with no update after the last one.

11 June 2026 · 1 days since the previous

Our Operations Team have been working very hard on this section and have managed to recover the water levels. We are able to reopen this length of canal from Lock 24E to Lock 8E.

10 June 2026 · 2 days since the previous

Our Operations Team are still working on the water levels and this section of the canal will still remain closed as the affected areas are still low. We will update the notice in the afternoon on Friday to give the section further time to recover.

Earlier updates · 3

8 June 2026 · 1 days since the previous

Our Operations Team are still working on the water levels and this section of the canal will still remain closed as the affected areas are still low. We will update the notice in the afternoon tomorrow to give the section further time to recover.

7 June 2026 · 1 days since the previous

Our operations team worked yesterday to make the affected boats safe, the canal will still be shut whilst the affected area are filling up. The canal will most likely be shut until tomorrow at the earliest where another update will be provided. Thank you for your understanding.

6 June 2026 · 0 days since the previous

Due to boater error the canal will be closed whilst our operatives refill the affected areas and make existing boats safe. This will be a lengthy operation so please bear with us. To be updated tomorrow 07 June 2026 at 10am.