Lock 43, Worcestershire

Scheduled: 4 January 2027 to 19 February 2027 (46 days planned), on the Worcester & Birmingham Canal. It has not started, so it is in no figure — see the archive's Coming up list.

Source: this notice on canalrivertrust.org.uk

Waterway
Worcester & Birmingham Canal
Region
West Midlands
Started
4 January 2027
Status
Scheduled
Days planned
46
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

145 days with no update after the last one.

30 April 2026 · 0 days since the previous

A navigation and towpath closure is required to carry out replacement of the bottom gate.