Hawkesbury Lock
Scheduled: 2 November 2026 to 6 November 2026 (4 days planned), on the Oxford Canal. It has not started, so it is in no figure — see the archive's Coming up list.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Oxford Canal
- Region
- West Midlands
- Started
- 2 November 2026
- Status
- Scheduled
- Days planned
- 4
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Lock
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Oxford Canal: Hawkesbury Lock to Hawkesbury Lock
Updates · 1
146 days with no update after the last one.
29 April 2026 · 0 days since the previous
A navigation closure is required to complete mortar repairs works on the coping stones at Hawkesbury Lock.