Canal closures

Independent. Built from Canal & River Trust's own published notices, with no affiliation to or endorsement by the Trust.

The archive / Chesterfield Canal

Worksop Town, Lock 50, Worksop

Scheduled: 11 January 2027 to 12 March 2027 (60 days planned), on the Chesterfield Canal. It has not started, so it is in no figure — see the archive's Coming up list.

Source: this notice on canalrivertrust.org.uk

Waterway
Chesterfield Canal
Region
Yorkshire and North East
Started
11 January 2027
Status
Scheduled
Days planned
60
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 1

148 days with no update after the last one.

27 April 2026 · 0 days since the previous

A navigation and towpath closure is required to carry out replacement of the top and bottom gates and repair works to the lock chamber

Cite this: Canal closures, “Worksop Town, Lock 50, Worksop”, https://crt-stoppages.pages.dev/notice/019dcf14-1fc3-784d-b54b-45eca03f88d4.

Every closure on Chesterfield Canal · Download the data · Method and limits