Bridge 1, Manchester Road Bridge
CRT cancelled this notice, so it never took effect. It is kept here because it was published, and it is excluded from every closure figure.
Source: this notice on canalrivertrust.org.uk
- Waterway
- South Dock
- Region
- London and South East
- Started
- 2 March 2026
- Status
- cancelled
- Days shut
- —
- CRT reason
- Repair
What CRT said it was for
We are pleased to confirm that the principal inspections carried out on Manchester Road Bridge last week have progressed ahead of schedule. As the work has been completed earlier than planned, the stoppage previously scheduled for 2–6 March will no longer be required.
Where
- South Dock: Bridge 1, Manchester Road Bridge to West India Dock Entrance Lock
Updates · 1
45 days with no update after the last one.
9 January 2026 · 0 days since the previous
A stoppage is required to carry out a principal inspection of the bridge. This will take place from 2–6 March, following an earlier stoppage scheduled for 16–20 February.