Bridges 118 to 119
A navigation closure on the Lancaster Canal, 7 October 2025 to 10 October 2025 — 3 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Lancaster Canal
- Region
- North West
- Started
- 7 October 2025
- Status
- Reopened 10 October 2025
- Days shut
- 3
- CRT reason
- Vegetation
- Cause
- Weather
- Asset
- Canal or river
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
What CRT said it was for
Navigation has resumed after the successful removal of the tree.
Where
- Lancaster Canal: Bridge 118, Hest Bank Bridge to Bridge 119, Hatlex Bridge
Updates · 2
1 days with no update after the last one.
9 October 2025 · 2 days since the previous
Navigation remains closed due to the large tree that has fallen between bridges 118 and 119 on the Lancaster Canal. Due to the recent Storm Amy our contractors are experiencing a high volume of work and we are currently awaiting confirmation of their attendance. We will provide a further update on Friday 10 October.
7 October 2025 · 0 days since the previous
A large tree has fallen and is currently blocking navigation between bridges 118 and 119 on the Lancaster Canal. Our teams have attended the site, however, due to the size of the tree we need to instruct our specialist contractor to assist with the removal. At present, we are unable to confirm when the contractor will be on site as adverse weather conditions from Storm Amy are impacting our waterways across the North West and causing delays. We will provide a further update on or before Thursday, 9th October.