Lock 4, Bosley

A navigation closure on the Macclesfield Canal, 13 October 2025 to 31 October 2025 — 18 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Macclesfield Canal
Region
North West
Started
13 October 2025
Status
Reopened 31 October 2025
Days shut
18
CRT reason
Repair
Cause
Struck by boat or vehicle
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 2

1 days with no update after the last one.

30 October 2025 · 27 days since the previous

We're pleased to confirm that works at Bosley Lock 4 are now nearing completion. The navigation will reopen from 10am on Friday 31st October.

3 October 2025 · 0 days since the previous

We apologise for the need to add a navigation closure to carry out essential repairs on the lock. This has become necessary following damage caused to the cill by a boat strike. As a result, the planned lock gate stoppage at nearby Lock 7 will now commence on 10/11/2025 to open the navigation and provide a 10-day window for boat movements between stoppages.