Cable Bridge East of Salford Junction

A navigation closure on the Birmingham & Fazeley Canal, 8 August 2025 to 3 October 2025 — 56 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Birmingham & Fazeley Canal
Region
West Midlands
Started
8 August 2025
Status
Reopened 3 October 2025
Days shut
56
CRT reason
3rd Party Works
Cause
Other cause
Asset
Bridge

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

What CRT said it was for

Works have been completed ahead of schedule and the canal and towpath are now reopened.

Where

Updates · 5

18 days with no update after the last one.

15 September 2025 · 28 days since the previous

We have received a further update from National Grid regarding the collapsed bridge. Scaffolding installation within the canal is scheduled to begin tomorrow. This will facilitate the safe dismantling and removal of the bridge structure. The installation is expected to take approximately one week, followed by around two weeks to remove the asbestos cladding and dismantle the bridge. Subject to progress on site, the aim is to reopen the canal and towpath by 4th October 2025. We will continue to share updates as the works progress. Thank you for your ongoing patience and understanding.

18 August 2025 · 7 days since the previous

We have received a further update from National Grid regarding the collapsed bridge. Unfortunately, the planned lift over the weekend could not take place due to unforeseen logistical challenges that prevented crane access to the site. National Grid are now exploring an alternative solution that involves installing a scaffold structure within the canal. This would allow the bridge to be dismantled and lowered onto the scaffold for safe removal. Based on this revised approach, the estimated timeframe for the full removal of the bridge is now approximately one month from today. We will provide a further update as soon as we receive one from National Grid

Earlier updates · 3

11 August 2025 · 3 days since the previous

National Grid are currently planning to lift the collapsed bridge over the weekend with the aim to reopen both the navigation and towpath by Monday 18th August. We will provide an update on or before Monday 18th August in case of any unforeseen delays.

8 August 2025 · 0 days since the previous

National Grid have confirmed that their current plan is to lift the collapsed bridge next week. Subject to final arrangements, they aim to reopen both the navigation and the towpath by the end of next week. They will be working over the weekend to finalise the dates, methodology, and programme of works. We expect to receive a confirmed timeframe for reopening by Monday.

8 August 2025 · 0 days since the previous

Please be advised that a National Grid cable bridge located east of Salford Junction has collapsed following a fire incident. As a result, the structure is currently obstructing both the navigation and the towpath. We are awaiting further information and will provide an update as soon as it becomes available.