Fenny Stratford Lock 22

A navigation closure on the Grand Union Canal, 28 July 2025 to 30 July 2025 — 2 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Grand Union Canal
Region
London and South East
Started
28 July 2025
Status
Reopened 30 July 2025
Days shut
2
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 5

0 days with no update after the last one.

30 July 2025 · 2 days since the previous

We are happy to advise the lock has now re-opened to all vessels.

28 July 2025 · 0 days since the previous

Following monitoring of the lock, please be aware the lock will be closed with the exception of assisted passage on 29th July 2025 between 10:00 and 12:00, after which it will remain closed until further notice. Unfortunately it is not possible to provide other times for assisted passage beyond this date.

Earlier updates · 3

28 July 2025 · 0 days since the previous

Following a further assessment of the lock, please be advised the lock will be closed to both Narrow Beams and Wide Beams.

28 July 2025 · 0 days since the previous

Please be advised that narrow beams will be able to use the lock, however access is fully restricted for wide beam vessels.

28 July 2025 · 0 days since the previous

Due to a broken balance beam the lock is closed whilst we undertake an assessment and repair.

Cite this: Canal closures, “Fenny Stratford Lock 22”, https://crt-stoppages.pages.dev/notice/0198505e-d47c-704f-af65-0e9a2f048720.

Every closure on Grand Union Canal · Download the data · Method and limits