Lock 37, Dashwood Lock
A navigation closure on the Oxford Canal, 3 November 2025 to 5 December 2025 — 32 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Oxford Canal
- Region
- London and South East
- Started
- 3 November 2025
- Status
- Reopened 5 December 2025
- Days shut
- 32
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Lock
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Oxford Canal: Lock 37, Dashwood Lock to Lock 37, Dashwood Lock
Updates · 2
0 days with no update after the last one.
5 December 2025 · 208 days since the previous
We're pleased to inform you that works on site have been completed ahead of schedule, and the navigation is now open. Please note: Our team is still carrying out some minor remedial work onsite, but this will not affect navigation.
11 May 2025 · 0 days since the previous
A navigation and towpath closure for top lock gate replacement and bottom lock gate repair.