Bridge 22, Burntacres Bridge
A navigation closure on the Rochdale Canal, 2 February 2026 to 27 February 2026 — 25 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Rochdale Canal
- Region
- Yorkshire and North East
- Started
- 2 February 2026
- Status
- Reopened 27 February 2026
- Days shut
- 25
- CRT reason
- Repair
- Cause
- Wear and tear
- Asset
- Bridge
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Rochdale Canal: Lock 13 to Lock 14
Updates · 3
116 days with no update after the last one.
3 November 2025 · 127 days since the previous
Following a recent review, we're now confident that the works can be completed within a shorter stoppage window. The revised stoppage dates are 2nd February to 27th February.
29 June 2025 · 52 days since the previous
This closure will now encompass two pieces of work. We will be doing offside abutment masonry repairs and general pointing to abutments below water level by Bridge 22, and Shaft blockage works to Lock 14. Please note the towpath will no longer be closed during these works.
8 May 2025 · 0 days since the previous
A navigation and towpath closure are required for offside abutment masonry repairs and general pointing to abutments below water level.