The archive / Rochdale Canal

Lock 8, Mayroyd - Near Hebden Bridge

A navigation closure on the Rochdale Canal, 5 January 2026 to 27 February 2026 — 53 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Rochdale Canal
Region
Yorkshire and North East
Started
5 January 2026
Status
Reopened 27 February 2026
Days shut
53
CRT reason
Repair
Cause
Wear and tear
Asset
Lock

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

Where

Updates · 2

22 days with no update after the last one.

5 February 2026 · 273 days since the previous

Following a detailed inspection after the canal was dewatered, we have identified that the repairs required are more extensive than originally anticipated. These works will now require specialist contractor involvement. To ensure the repairs are completed safely and to the required standard, this stoppage will now remain in place until 27 February. Thank you for your patience and understanding while we complete these essential works.

8 May 2025 · 0 days since the previous

A navigation and towpath closure are required for wash wall repair works on the downstream lock landing.