HS2 Oxford Canal Viaduct, nearest structure is OX-057-002, Wormleighton, Warwickshire
A navigation closure on the Oxford Canal, 12 November 2025 to 14 November 2025 — 2 days.
Source: this notice on canalrivertrust.org.uk
- Waterway
- Oxford Canal
- Region
- West Midlands
- Started
- 12 November 2025
- Status
- Reopened 14 November 2025
- Days shut
- 2
- CRT reason
- 3rd Party Works
- Cause
- Nothing failed
- Asset
- Other
Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.
Where
- Oxford Canal: Bridge 127, Stoneton Bridge to Bridge 128, Willisons Bridge
Updates · 2
14 days with no update after the last one.
31 October 2025 · 178 days since the previous
The contractor building the HS2 viaduct over the Oxford Canal no longer requires the full duration of the November 2025 navigation stoppage to undertake their planned works. The works will start on 12 November 2025 instead of 3 November 2025. Post Christmas stoppage of the canal will still be required at this location by HS2's contractor. Towpath users will be directed onto an established towpath diversion route around the works.
6 May 2025 · 0 days since the previous
A navigation and towpath closure are required for construction works for a new high speed 2 railway viaduct.