Maida Hill Tunnel Closed

A navigation closure on the Regent's Canal, 29 April 2025 to 6 May 2025 — 7 days.

Source: this notice on canalrivertrust.org.uk

Waterway
Regent's Canal
Region
London and South East
Started
29 April 2025
Status
Reopened 6 May 2025
Days shut
7
CRT reason
Information
Cause
Other cause
Asset
Tunnel

Cause and asset are read from the notice prose, not CRT fields; the reason above is CRT's own.

What CRT said it was for

Maida Hill Tunnel is now open

Where

Updates · 3

4 days with no update after the last one.

2 May 2025 · 0 days since the previous

Further Update: Specialist contractors have started to empty the generator tanks and will continue overnight. Clean up of the canal is underway and the western portal has been skimmed today and booms still in place. We plan to start to draw the water through the tunnel tomorrow by using Camden lock and collecting the oil as it exits. All being well we are hoping to have the tunnel and therefore navigation back open Friday afternoon. If there is any change to this timeline then the notice will be updated accordingly.

2 May 2025 · 0 days since the previous

The emergency services have been on site all night and continue to be incident control. We are continuing to work closely with them and contractors on site from National Grid to contain the pollution and to start to develop a plan to clear up now that the fire is out and temperature more manageable. This is an evolving situation and we will look to provide a further update later today. The tunnel will continue to be closed until the clean up is complete. We continue to request that boaters do not move in the affected area to help minimise the spread of pollution

2 May 2025 · 3 days since the previous

Please be advised that due to an environmental pollution incident related to the fire at St Johns Wood Substation, Maida Hill tunnel has been closed. Updates will be provided when available This notice was originally posted on an old system which has now been upgraded, the original description and latest update have been transferred here. To view any historical updates related to this notice, please click here (link to file).