Fossdyke Canal
4.8 closure-days per kilometre (95% range 3.8–5.8) — 86 days across 5 closures of this 18km canal.
Lengths from CRT's ArcGIS open data, published under the strictest reading of its licence. A notice is attributed to the whole named waterway, not to a point.
Nothing is shut on this canal today.
- Regions
- East Midlands
- On record
- 5 closures
Every closure on record
Showing all 5 closures on the Fossdyke Canal.
5
closures
86
closure-days
0
in cruising season
0
no reopening date
What these figures mean
- Population
- Which closures a figure counts. All closures is everything; Unplanned, in season drops CRT's scheduled winter programme and any day outside the 15 March to 31 October cruising season; CRT winter programme is that maintenance alone.
- Defensible duration
- The days between a closure's start and its reopening date, counted only where the dates allow it. A cancelled notice, or one whose reopening precedes its start, has no defensible duration and is in no total.
- Closure-days
- One day on which one closure was in force. Two closures on the same day are two closure-days; where the question is how long a canal was actually disrupted, overlapping notices are unioned into single intervals.
May 25Jun 25Jul 25Aug 25Sep 25Oct 25Nov 25Dec 25Jan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26
| Notice | Extent | Started | Days |
|---|---|---|---|
| Torksey Flood Gates | Fossdyke Canal - 001 | 2026-01-22 | 34 |
| Torksey Flood Gates | Fossdyke Canal - 001 | 2025-11-30 | 29 |
| Lock 1, Torksey Lock | Lock 1, Torksey Lock | 2026-01-10 | 10 |
| Torksey Flood Gates | Fossdyke Canal - 001 | 2025-11-14 | 7 |
| Lock 1 Torksey Lock | Torksey Trentside, EA Flood Gates | 2026-02-28 | 6 |
Showing the 5 longest of 5. Every row links to the notice CRT published.