Bugsworth Arm (Peak Forest Canal)
No closures are on record for this canal in the current season.
- Regions
- North West
- On record
- 2 closures
Every closure on record
Showing all 2 closures on the Bugsworth Arm (Peak Forest Canal).
2
closures
49
closure-days
49
in cruising season
0
no reopening date
What these figures mean
- Population
- Which closures a figure counts. All closures is everything; Unplanned, in season drops CRT's scheduled winter programme and any day outside the 15 March to 31 October cruising season; CRT winter programme is that maintenance alone.
- Defensible duration
- The days between a closure's start and its reopening date, counted only where the dates allow it. A cancelled notice, or one whose reopening precedes its start, has no defensible duration and is in no total.
- Closure-days
- One day on which one closure was in force. Two closures on the same day are two closure-days; where the question is how long a canal was actually disrupted, overlapping notices are unioned into single intervals.
May 25Jun 25Jul 25Aug 25Sep 25Oct 25Nov 25Dec 25Jan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26
| Notice | Extent | Started | Days |
|---|---|---|---|
| Bugsworth Basin | Bridge 56 to Bridge 61, Chinley Road Bridge | 2025-08-01 | 49 |
| Bugsworth Arm | Bridge 56 | 2025-10-03 | same day |
Showing the 2 longest of 2. Every row links to the notice CRT published.